P-02 · Apartment
Nasr City apartment
A 25-year-old flat: we replaced the old groundwork and opened the kitchen to the dining area.
- Location
- 7th District, Nasr City
- Area
- 120 m²
- Duration
- 9 weeks
- Level
- Standard


Scope of work
- Removing old tiles and plaster
- New pipes and drains
- Open kitchen with stone counter
- Tiles and paint
Materials
- First-grade Egyptian tiles
- Quartz counter
- Concealed mixers
Stages
The actual schedule in weeks (9 weeks). Some stages overlap because crews work in parallel.
- Strip-outWeek 1–2
- New groundworkWeek 2–4
- Plaster and tilesWeek 4–6
- Kitchen and paintWeek 6–8
- HandoverWeek 8–9
Gallery




Have a similar unit?
Get a rough cost, or book a visit and we'll write you a quotation.