P-05 · Villa

El Shorouk villa

A family villa renovation: a bare-brick roof turned into an open terrace, two kitchens and bathrooms rebuilt from scratch.

Location
El Shorouk City
Area
280 m²
Duration
18 weeks
Level
Premium
The El Shorouk villa roof terrace after finishing, from the same angleThe El Shorouk villa roof terrace before finishing: bare plaster and concrete floor
Drag the line or use the arrow keys to compare.

Scope of work

  • Strip-out and new groundwork
  • Roof terrace with waterproofing, floors and a timber canopy
  • Two kitchens and four bathrooms

Materials

  • Anti-slip outdoor porcelain
  • Imported porcelain
  • Roof waterproofing

Stages

The actual schedule in weeks (18 weeks). Some stages overlap because crews work in parallel.

  1. Strip-outWeek 1–3
  2. Groundwork and waterproofingWeek 3–7
  3. Roof and floorsWeek 7–12
  4. Kitchens and bathroomsWeek 10–15
  5. Paint and handoverWeek 15–18